[Mar-2023] Exam Sure Pass SAP Certification with E_S4HCON2022 exam questions [Q39-Q56]

Share

[Mar-2023] Exam Sure Pass SAP Certification with E_S4HCON2022 exam questions

Real SAP E_S4HCON2022 Exam Questions Study Guide


SAP S/4HANA Conversion and SAP System Upgrade Certification Exam Topics:

Topic AreasTopic Details, Courses, BooksWeighting
Manual Activities for SUMDescribe the necessary manual preparation and follow-on activities for SUM

ADM328

8% - 12%
SUM Execution PartPerform the SUM execution part, including DMO

ADM328

> 12%
Handling of an SAP System LandscapeDescribe the handling of the SAP system landscape during SAP S/4HANA conversion and SAP system upgrade

ADM328

8% - 12%
DowntimeDescribe the factors influencing downtime and techniques to reduce downtime

ADM328

8% - 12%
Modification AdjustmentPerform the modification adjustment with SPDD and SPAU

ADM328

8% - 12%
SAP S/4HANA Conversion Prepare PhaseDescribe and perform the actions necessary during the SAP S/4HANA conversion prepare phase

ADM328

> 12%
SUM Monitoring and TroubleshootingMonitor and troubleshoot the SUM procedure

ADM328

8% - 12%

 

NEW QUESTION 39
You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.

  • A. The transport between Unicode and non-Unicode systems is forbidden.
  • B. The transport domain of systems DEV and QAS must differ from the transport domain of system PRD.
  • C. The upgrade of the PRD must be finished before you start new development in the DEV.
  • D. The upgrade of the PRD must be finished before you import any transports from the upgraded DEV system into the PRD.

Answer: D

 

NEW QUESTION 40
You are performing an SAP S/4HANA conversion for your production system. This conversion requires that certain business functions are switched on.
Following SAP recommendations, how will you achieve this?
There are 2 correct answers to this question.
Response:

  • A. During conversion, SUM delivers some business functions already activated.
  • B. Specify the business functions that need to be switched on during the prepare part of SUM.
  • C. Activate the required business functions manually in the production system.
  • D. Import a transport request from the development system that contains the recording of the activation.

Answer: A,D

 

NEW QUESTION 41
ICNV initialization does 3

  • A. Creation of views
  • B. AA
  • C. Build index on flag column
  • D. Creation of flag

Answer: A,C,D

 

NEW QUESTION 42
You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.

  • A. SAP S/4HANA conversion including database migration and Unicode conversion
  • B. Unicode conversion SAP S/4HANA conversion without database migration Database migration
  • C. Unicode conversion Upgrade to SAP ECC with SAP_BASIS 750 including database migrationSAP S/4HANA conversion without database migration
  • D. Unicode conversion SAP S/4HANA conversion including database migration
  • E. Unicode conversion Database migration SAP S/4HANA conversion without database migration

Answer: C,D,E

 

NEW QUESTION 43
What do you need to consider when performing the SI checks for an SAP S/4HANA conversion? There are 2 correct answers to this question.

  • A. Depending on the SAP S/4HANA version, there are different SI check frameworks.
  • B. You need an SAP system based on AS ABAP 7.50 or above for the SI check framework.
  • C. You need to build up a SI check framework by applying SAP notes.
  • D. The SI checks are executed in the development system and the results are transported into the subsequent systems.

Answer: A,C

 

NEW QUESTION 44
Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?

  • A. Silent data migration (SDM)
  • B. Shadow on target creation
  • C. Downtime conversion
  • D. Downtime migration

Answer: D

 

NEW QUESTION 45
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.

  • A. Standalone AS ABAP with SAP_BASIS 752 and above
  • B. SAP Solution Manager 7.2
  • C. SAP ECC system from SAP ERP 6.0 EHP 8
  • D. SAP S/4HANA Server 1809 and above

Answer: A,D

 

NEW QUESTION 46
Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system, before SUM continues?
There are 2 correct answers to this question.
Response:

  • A. Manually activate the adjusted dictionary objects
  • B. Create "modified* versions of the objects that you need to adjust
  • C. Release the transport request containing the modification adjustment
  • D. Assign the transport request as a modification adjustment transport

Answer: B,D

 

NEW QUESTION 47
You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?
There are 3 correct answers to this question.
Response:

  • A. Import of dictionary objects from the download directory in phase DDIC_UPG
  • B. Import of upgrade and language data from the download directory in phase TABIM UPG
  • C. Activation of dictionary objects in phase ACT_UPG
  • D. Generation of the new ABAP loads in phase RUN_SGEN_GENER8
  • E. Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE

Answer: A,B,C

 

NEW QUESTION 48
In ICNV. How database operations synchronized between the source and the target table?

  • A. AA
  • B. Deletes are directly executed in the target table by delete trigger.

Answer: B

 

NEW QUESTION 49
In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?
There are 2 correct answers to this question.
Response:

  • A. Upgrading to SAP ECC 6.08 without using DMO
  • B. SAP S/4HANA conversion to SAP S/4HANA 1709
  • C. Updating to SAP ECC 6.07 using DMO
  • D. Using DMO when applying Support Packages to SAP ECC 6.07

Answer: A,B

 

NEW QUESTION 50
What can you achieve by setting the SUM parameter "migration_only" to 1 in parameter file SAPup_add.par?
Please choose the correct answer.
Response:

  • A. An SAP S/4HANA conversion is performed, without adapting the customer data.
  • B. A change of the database type is performed, without changing the software components.
  • C. A migration of the SAP system to a new hardware is performed, without performing an SAP S/4HANA conversion.
  • D. An upgrade of the software components is performed, without changing the database type.

Answer: B

 

NEW QUESTION 51
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?

  • A. The end of the business downtime
  • B. The start of the business downtime
  • C. The end of the database migration
  • D. The start of the Execution roadmap step

Answer: A

 

NEW QUESTION 52
During a SUM run you want to check if the phase SHADOW_IMPORT_INC is still running properly. Where can you find information about this?
There are 2 correct answers to this question.
Response:

  • A. Check for running batch jobs in the shadow system via Job Overview (SM37)
  • B. Check for the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp
  • C. Check for running R3trans processes on the host of the primary application server
  • D. Check for running R31oad processes on the host of the primary application server

Answer: B,C

 

NEW QUESTION 53
You are executing a standard SUM procedure to update an SAP system using main configuration mode "Standard". When will the shadow system be stopped for the last time?
Please choose the correct answer.
Response:

  • A. Before the downtime starts
  • B. Early in the downtime
  • C. As part of the cleanup process
  • D. At the end of the downtime

Answer: A

 

NEW QUESTION 54
Unicode migration ECC on MaxDB to HANA in scale out what should we consider.

  • A. Target DB size will increase temporarily
  • B. A
  • C. DMO can only be run with systems NW740 or NW731

Answer: A,C

 

NEW QUESTION 55
You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction".
Where can you change this during the migration via the Utilities option of the SUM UI?
There are 2 correct answers to this question
Response:

  • A. In Process Control Center
  • B. In SUM Phaselist
  • C. In DMO Migration Preparation
  • D. In SUM Parameters

Answer: A,D

 

NEW QUESTION 56
......

Updated and Accurate E_S4HCON2022 Questions for passing the exam Quickly: https://testking.vcetorrent.com/E_S4HCON2022-valid-vce-torrent.html